99 Bishopsgate

Brookfield Properties

9,000 sq. ft. fit-out as a Show Floor for potential tenants.

Scope of works

Suspended Ceiling and Dry Lining package

Installation of new SAS 330 System ceiling with Fire Barriers installed within the ceiling void. Plasterboard margins to the external & internal elevations, the external margin incorporating a recessed ‘Blind Box’ detail.

Relining of existing core wall & perimeter columns including re-construction of Shaftwall service ducts.

New WC’s were constructed within the existing cores with drywall partitions, gyplyner wall linings & plasterboard ceilings.

The Goods lift lobby area were also refurbished with re-lining of walls and installation of bespoke metal plank tile ceiling.

MAIN CONTRACTOR: ISG Plc

ARCHITECT: HLW International LLP

PROJECT VALUE: £150,000.00